AWASH RIVER CHANNELIZATION WORK AND RIVER DIVERSION CUTOFF WORK

photo_2024-09-19_14-58-08

Project Description

CLIENT : ECWC
CONSULTANT :ECDSE

LOCATION : AFAR REGION/ KESEM / AMBIRA WOREDA

PROJRCT COST IN BIRR : 77,560,000

PROJECT COST IN USD : 1,491,538.46

PROJECT SIGN DATE : MAY 2022 & SEPTEMBER 2022

 

DAMAGED RE-CONSTRUCTION OF MAIN LIBRARY BUILDING OF DESSIE CAMPUS

photo_2024-09-30_19-10-13

Project Description

CLIENT : WOLLO UNIVERSITY
CONSULTANT :MTT CONSULTING ARCHITECTS AND ENGINEERS PLC
LOCATION : DESSIE
STATUS : COMPLETED
PROJECT COST IN BIRR :143,607.543 65

PROJECT COST IN USD :2,478,128.45

PROJECT SIGNED DATE : 30/10/2014

BESHALECONDOMINIUMASPHALT

photo_2024-09-19_15-32-53

Project Description

CLIENT: ADDIS ABABA CITY ROAD AUTHORITY
CONSULTANT: GOGOT CONSULTING ENGINEERS PLC
LOCATION: ADDIS ABABA
PROJECT STATUS- ON PROGRESS
PROJECT COST IN ETB
343,773,940.65
PROJECT COST IN USD
$8,572,210.78

JIMMA CITY G+5 ADMINISTRATION BUILDING

photo_2024-09-23_09-54-48

JIMMA CITY G+5 ADMINISTRATION BUILDING

Client:   Jimma City Administration
Consultant:  ETHIOPIAN ENGINEERING CORPORATION BUILDING AND URBAN SECTOR
Location: Jimma
Status: In Progress
Project Cost in ETB: 410,084.604.64

Project Cost in USD : 7,076,524.67

DILLA UNIVERSITY DORMITORY BUILDING

photo_2024-09-21_10-31-06

DILLA UNIVERSITY DORMITORY BUILDING

Client:   Dilla University
Consultant:   Gereta Consult PLC
Location:   Dilla
Status: Completed
Project Cost in ETB: 698,967,565,30

Project Cost in USD:12,061,562.86

Completed

DIRE DAWA UNIVERSITY LIBRARY AND HIGHER CLINIC

DIRE DAWA UNIVERSITY LIBRARY AND HIGHER CLINIC

Client:Dire Dawa University
Consultant:Acute Engineering PLC
Location:Dire Dawa
Project Status: COMPLETED 

Project Cost in ETB:712 870 871,79

Project Cost in USD: 12,301,481.83

Opening Ceremony:

GERADO BUS STATION

photo_2022-09-14_19-18-09

GERADO BUS STATION

Client:   Dessie City Administration
Consultant: Ethiopian Construction Design & Supervision Works Corporation Building And Urban Design
Location:   Dessie
Status: In Progress
Project Cost in ETB:   115, 412, 659.84
Project Cost in USD: $3, 371, 090.66

WOLLO UNIVERSITY CENTRAL CORE LABORATORY

WhatsApp Image 2024-09-23 at 20.09.10_03c4535a

WOLLO UNIVERSITY CENTRAL CORE LABORATORY

Client:  Wollo University
Consultant:   Yohannes Abay Consulting Architects & Engineers 
Location:   Dessie
Status: In Progress
Project Cost in ETB: 536,535136.81

Project Cost in USD:9,258,587.35

 

Completed

AWASH INTERNATIONAL BANK BRANCH BUILDING

AWASH INTERNATIONAL BANK BRANCH BUILDING

Client:  Awash International Bank
Consultant: MTT Consulting Architects & Engineers PLC
Location:  Bale Robe
Status: COMPLETED
Project Cost in ETB: 194,978,658.300

Project Cost in USD: 3,364,601.5

B+G+4 Construction Work Completed

photo_2023-12-27_17-26-39

GOBA 2B+G+8 TEACHING HOSPITAL

GOBA 2B+G+8 TEACHING HOSPITAL

Client:   Madda Welabu University
Consultant:   MTT Consulting Architects & Engineers PLC
Location:   Bale Robe
Status: 76% Completed
Project Cost in ETB:   1, 797, 671, 873,.12
Project Cost in USD: $77, 543, 345.63

Site Visit

WhatsApp Image 2024-09-23 at 19.34.39_a4a182da - Copy - Copy